Construction Updates


Welcome!

San Francisco Day School is embarking on a long-intentioned promise to our community and for our students—to update, expand, and improve our facilities to match the exceptional educational program at SF Day. This webpage is your resource for all things project-related, and we look forward to keeping you informed as construction is underway.

We are honored to be a part of our greater community and as always, it is our goal to remain good neighbors throughout this process. Please feel free to reach out if we can provide additional information or be of help.

Project Status

Please bookmark this page (www.sfday.org/construction) for ongoing updates. 

Last update: November 29, 2021

Here is the upcoming work for the next two weeks. Also, scroll to the bottom of the page for an overview of construction through the completion of the project.

 

Below is a high level schedule of the remaining work through the completion of construction.  

Week of 11/29:  Noise levels expected to be low for the majority of the week.

  • Interior Painting Touch-up and Final Coat – low noise
  • Miscellaneous Interior Finish Installation – low noise
  • Final Clean at Building Interior – low noise
  • Exterior Electrical & Lighting Trim – low noise
  • Waterproofing Repair at Existing School – low noise
  • South Ramp Handrail and Paver Install – low/moderate noise
  • Concrete Placement Wall Infill – moderate noise & large vehicle traffic
  • Curb and Gutter Demo – high noise & large vehicle traffic
  • Sidewalk, Curb, & Gutter Grading, Formwork, and Concrete Placement – moderate noise & large vehicle traffic
  • MEP System Startup and Testing– low noise

Week of 12/6:  Noise levels expected to be low for the majority of the week.

  • Miscellaneous Interior Finish Installation – low noise
  • Final Building Clean – low noise
  • Waterproofing and Plaster Repair at Existing School – low noise
  • Sidewalk, Curb, & Gutter Grading, Formwork, and Concrete Placement – moderate noise & large vehicle traffic
  • MEP System Final Testing and Inspections – low noise

For further questions regarding the construction site, please contact Bodie Bloyd at bbloyd@herrero.com

Frequently Asked Questions

At A Glance

Project Start Date 
July 13, 2020

Target Completion Date
November 2021

Architect
Studio Bondy Architecture

Construction
Herrero Builders, Inc.

Contacts
If you have a question or concern during the project, please contact:

Site Safety
Bodie Bloyd,
Herrero Builders; Site Superintendent:
bbloyd@herrero.com or
415-405-6095

Project
Mara Chase, projectFOCUS; Owner's Representative:
mara@project-focus.net

School
neighbor@sfday.org or
415-568-3600