Construction Updates


Welcome!

San Francisco Day School is embarking on a long-intentioned promise to our community and for our students—to update, expand, and improve our facilities to match the exceptional educational program at SF Day. This webpage is your resource for all things project-related, and we look forward to keeping you informed as construction is underway.

We are honored to be a part of our greater community and as always, it is our goal to remain good neighbors throughout this process. Please feel free to reach out if we can provide additional information or be of help.

Project Status

Please bookmark this page (www.sfday.org/construction) for ongoing updates. 

Last update: April 19, 2021

Week of 4/19:  Noise levels expected to be high for the majority of the week with frequent large vehicle traffic. Saturday work planned for 4/24.

  • Metal Decking Installation – high noise
  • Structural Steel Installation – moderate/high noise and large vehicle traffic
  • Structural Steel Welding – moderate noise
  • Steel Stair Installation – moderate/high noise and large vehicle traffic
  • Misc. Concrete Placement – moderate noise and large vehicle traffic
  • Fire Water Service Line Installation – moderate/high noise and large vehicle traffic
  • MEP Sleeve Installation at Addition Decking – low noise
  • Rebar Installation and Miscellaneous Formwork at Addition Decking – moderate noise
  • Metal Stud Layout & Framing – moderate noise
  • Mechanical, Electrical, & Plumbing Installation – low to moderate noise
  • Miscellaneous Carpentry at Residence – moderate noise
  • Tile Installation at Residence – low noise
  • Tape & Mud at Residence – low noise

 

Week of 4/26:  Noise levels expected to be high for the majority of the week with frequent large vehicle traffic. Saturday work planned for 4/24.

  • Metal Decking Installation – high noise
  • Structural Steel Welding – moderate noise
  • Steel Stair Installation – moderate/high noise and large vehicle traffic
  • Concrete Placement for L1 and L2 Decks – moderate noise and large vehicle traffic
  • MEP Sleeve Installation at Addition Decking – low noise
  • Rebar Installation and Miscellaneous Formwork at Addition Decking – moderate noise
  • Metal Stud Layout & Framing – moderate noise
  • Mechanical, Electrical, & Plumbing Installation – low to moderate noise
  • Miscellaneous Carpentry at Residence – moderate noise
  • Flooring Installation at Residence – low noise

For further questions regarding the construction site, please contact Bodie Bloyd at bbloyd@herrero.com

Frequently Asked Questions

At A Glance

Project Start Date 
July 13, 2020

Target Completion Date
November 2021

Architect
Studio Bondy Architecture

Construction
Herrero Builders, Inc.

Contacts
If you have a question or concern during the project, please contact:

Site Safety
Bodie Bloyd,
Herrero Builders; Site Superintendent:
bbloyd@herrero.com or
415-405-6095

Project
Mara Chase, projectFOCUS; Owner's Representative:
mara@project-focus.net

School
neighbor@sfday.org or
415-568-3600