Construction Updates


Welcome!

San Francisco Day School is embarking on a long-intentioned promise to our community and for our students—to update, expand, and improve our facilities to match the exceptional educational program at SF Day. This webpage is your resource for all things project-related, and we look forward to keeping you informed as construction is underway.

We are honored to be a part of our greater community and as always, it is our goal to remain good neighbors throughout this process. Please feel free to reach out if we can provide additional information or be of help.

Project Status

Please bookmark this page (www.sfday.org/construction) for ongoing updates. 

Last update: October 16, 2020

Here is the upcoming work for the next two weeks:

Week of 10/19:  Noise levels expected to be low/moderate for the majority of the week with some minor vibrations and moderate traffic.

  • Off-haul of Soil – moderate noise and large vehicle traffic
  • Backfill and Compaction for Underground Utilities – moderate noise and low vibrations
  • Below Slab Electrical Conduit Install – low noise
  • Subgrade Preparation and Foundation Excavation – low/moderate noise and low vibrations
  • Rebar and Formwork ADU Slab – moderate noise
  • Concrete Placement for Residence Slab – moderate noise and large vehicle traffic
  • Wood Framing – moderate noise
  • Plumbing and Electrical Wall Rough-in – low noise

Week of 10/26:  Noise levels expected to be low/moderate for the majority of the week with moderate traffic.

  • Below Slab Electrical Conduit Install – low noise
  • Drain Rock Delivery and Placement – moderate noise and large vehicle traffic
  • Waterproofing and Vapor Barrier Installation – low noise
  • Wood Siding Removal – moderate noise
  • Wood Framing – moderate noise
  • Plumbing and Electrical Wall Rough-in – low noise

For further questions regarding the construction site, please contact Bodie Bloyd at bbloyd@herrero.com

Frequently Asked Questions

At A Glance

Project Start Date 
July 13, 2020

Target Completion Date
November 2021

Architect
Studio Bondy Architecture

Construction
Herrero Builders, Inc.

Contacts
If you have a question or concern during the project, please contact:

Site Safety
Bodie Bloyd,
Herrero Builders; Site Superintendent:
bbloyd@herrero.com or
415-405-6095

Project
Mara Chase, projectFOCUS; Owner's Representative:
mara@project-focus.net

School
neighbor@sfday.org or
415-568-3600